Gantt chart
Quiz by Dharshani Jayasuriya
Feel free to use or edit a copy
includes Teacher and Student dashboards
Measure skillsfrom any curriculum
Measure skills
from any curriculum
Tag the questions with any skills you have. Your dashboard will track each student's mastery of each skill.
With a free account, teachers can
- edit the questions
- save a copy for later
- start a class game
- automatically assign follow-up activities based on students’ scores
- assign as homework
- share a link with colleagues
- print as a bubble sheet
10 questions
Show answers
- Q1What is the primary purpose of a Gantt chart?To visually represent project schedulesTo perform financial analysisTo draft marketing strategiesTo manage customer relations30s
- Q2Which of the following elements is NOT typically included in a Gantt chart?Task durationDependencies between tasksStart and end datesBudget allocation30s
- Q3In a Gantt chart, what does a horizontal bar represent?A budget limitA resource allocationA project milestoneA task duration30s
- Q4How can a Gantt chart help in project management?By showing task sequences and timelinesBy generating marketing leadsBy tracking team performance metricsBy managing financial transactions30s
- Q5What kind of projects benefit the most from using a Gantt chart?Projects without deadlinesProjects with multiple tasks and deadlinesProjects with unlimited budgetsSingle-task projects30s
- Q6What is the significance of dependencies in a Gantt chart?They show the relationship between tasksThey indicate financial costsThey represent team members' rolesThey define the project scope30s
- Q7Which software tool is commonly used to create Gantt charts?Adobe PhotoshopMicrosoft ProjectMicrosoft WordExcel30s
- Q8What information is typically found along the vertical axis of a Gantt chart?List of tasksProject budgetTimeline of the projectTeam member names30s
- Q9What does it indicate if a Gantt chart shows overlapping bars for different tasks?The tasks are dependent on each otherThe tasks are the sameThe tasks can be worked on simultaneouslyThe project is behind schedule30s
- Q10Which of the following best describes a milestone in a Gantt chart?A budget estimate for the projectA significant point in the project timelineAn employee performance review dateA task that requires extensive resources30s