1. An Agile team is discussing each user story in the iteration backlog and documenting the conditions of satisfactions for each story. These conditions are then written on the back of the story cards. What is the team doing?
2. Your project is dependent on the output of a deliverable being created by another project team. That deliverable is three weeks late, a fact that you communicated in your weekly status reports. At the most recent company-wide status meeting, the manager of that project reported that the project is on time. What should you do?
3. Which of the following is an estimation technique that uses the values of cost, budget, and duration from a previous similar activity as the basis of activity?
4. You have recently been hired as a senior business analyst on a complex system integration project. The chief programmer has asked you to review the project BRD prior to arranging a meeting with him. What is a BRD?
5. Bill is the project manager of a software project that was originally estimated to be completed in 12 months. Assuming past performance is indicative of future performance, the Estimate at Completion (EAC) can be calculated as:
6. A set of procedures that describe how modifications to the project deliverables and documentation will be managed and controlled is part of:
7. The ability of a product to cope with unforeseen failures and quickly recover is known as:
8. According to Frederick Herzberg, which of the following is not a hygiene factor?
9. Ideally all Agile team members should be 100% dedicated to the project. While this condition is ideal, it sometimes cannot be met. What is the key problem when team members are not 100% dedicated?
10. Decision tree analysis can use the information generated from which of the following techniques to populate the branches of the decision tree?
11. You are leading an Agile team developing a marketing website for a new entrant in the telecommunication industry. For this project, who is accountable for the development of the underlying database management system?
12. A project uses rounding of activity cost estimates data to the nearest $100, uses staff hours as the unit of measure for resources, and has a variance threshold of 10 percent deviation from the baseline plan. These approaches are typically documented in the: