PMP (Agile) Questions
Quiz by Amer ali
Tag the questions with any skills you have. Your dashboard will track each student's mastery of each skill.
An agile project sponsor has requested to see the impact of the scope changes requested by the customer throughout the lifecycle of the project. What information radiator would an agile practitioner recommend to the sponsor to look at?
In an Agile project, who plays the role of a servant leader?
Todd is a directive PMO of an IT organization. As an Agile expert, he decides to promote osmotic communication across projects under his portfolio. Osmotic communication is best suited in which of the following team environments?
An Agile project using scrum methodology with relatively fixed scope is running behind schedule for last 3 sprints. What may be the reason for such a delay?
In a typical agile project, Product backlog is the repository for product scope. Who owns the product backlog?
Team members are not happy as the product owner often sets up informal meetings for project status update, which is impacting their scheduled plan to meet the iteration goal. What can be Servant Leader’s best course action to manage the given situation?
Scrum is a popular agile framework. Which of the following represents a scrum artifact?
Which of the following Agile principles helps to promote elimination of wastes thereby minimizing scope creep and encouraging to do only those categories of work that generates business value?
In a Sprint review meeting, the product owner dismisses the sprint and recommends the newly appointed Scrum Master to arrange Agile coaching for the team. Team really worked hard to meet the sprint goal and came up with a detailed PowerPoint presentation for the sprint review meeting. What went wrong in the situation mentioned above?
Tom is a Project Manager of a software development project. During the preparation of Project Management Plan, he decides to use Agile development approach instead of traditional waterfall approach which is widely used in his organization. What has influenced him to decide agile as a development approach?
In an Agile Software development project, a tester is writing a test before work related to coding has begun. Which of the following technical practices is mentioned in the given scenario?
Tom is a Servant leader of a complex software development project that is running using Agile development approach. Two developers are having difference in opinion about the technical approach of a user story. What needs to be done in this situation?
The project team is using Iteration burn-down chart to predict the remaining work in the current iteration backlog. Iteration Burn-down chart is an example of which of the following tools and techniques?
Which of the following is not an example of the four values of the Agile Manifesto?
Tom is the newly appointed Project Manager of a software development project which has high degree of uncertainties and scope is not yet fully defined. Considering all the factors, he decides to adopt Agile development approach for running the project. Now, he has to come up with an initial cost estimate before the project work begins. What can be the best approach for the preparation of initial cost estimate as per the stated scenario?
Todd is a project manager of a very large software product development project that needs to be executed from five different cities. Senior management has decided to run the project using an agile approach by following the philosophies of the scrum as much as possible. What framework is most suited as per the given situation?
At a walkthrough, a stakeholder, end user, and the development team identify significant new functionality required for the proposed solution to be effective. What is the next step?
Stakeholders want to understand what progress an agile team has made in their last iteration. What should stakeholders review to determine this information?
The ongoing sprint for a software development project that is being executed by following Agile - Scrum development approach needs to be cancelled as the sprint goal has become obsolete due to a sudden change in law associated to IT security.
The Scrum Master explains the three primary roles in Scrum to the newly hired team member. Which role is sometimes called 'the voice of the customer’?
In a typical business complex and mid-sized agile project, what does the team attempt to develop every Sprint?
The product owner of an agile project has the responsibility of grooming the product backlog. Grooming involves prioritizing and re-prioritizing user stories on a regular basis. As an agile best practice, which of the following criteria are most important for the owner to use when grooming the product backlog?
A scrum team that has been working on an agile project, is arguing over the story points in the sprint meeting planning. The product owner is pushing the team to complete 170 story points of user stories in the next sprint whereas the average velocity of the development team is 150 story points per sprint. Who will make the final decision to fix the number of story points to be completed in a sprint?
Which of the following is not a feature of an Agile team?
On the completion of the first three iterations, an agile team determined that 344 story points are required to complete the remaining project. The average team velocity in the first three iterations was 50 story points. What will be the number of iterations required for the team to complete the project?
An agile team finished coding for the current iteration. Which of the following is a continuous process improvement ceremony that the team will now attend?
An agile team is working on a project for which the user stories have not been tested sufficiently. What could be the reason behind it?
One role of an agile practitioner is to promote the knowledge and execution of agile practices within an organization. Which of the following agile practitioners is responsible for the creation and maintenance of the product roadmap?
A team lead is currently demonstrating a potentially shippable product increment for project stakeholders. Which agile meeting is being conducted?
At the sprint retrospective meeting, the team lead drew a fishbone diagram, wrote a problem at the head of the fish, and labeled the bones of the fish with categories. What should the team do next?