PMP (Closing) Questions
Quiz by Amer ali
Tag the questions with any skills you have. Your dashboard will track each student's mastery of each skill.
A key output of the Close Project process is the finalization and archive of the lessons learned register. The register contains information related to best practices identified, project successes and failures, and ideas for future improvements. When during the project should information have been added to the lessons learned register?
In executing the Close Project process, you have created a final project report, transferred the final product to the ownership of the customer, and dismissed your project team. You believe that you can now formally close the project. What activity have you forgotten to complete?
You have just left the final project meeting, during in which you officially transferred ownership of the final product to the customer. In which previous Monitoring and Controlling process did the same customer formally accept the project deliverables?
During the process of completing the Close Project process, you lead your team in analyzing what was planned versus what the results were in the project. The aim of your analysis is to define methods to improve future projects. What data analysis technique are you utilizing?
Unfortunately, this morning you received notification that your project. was canceled. What is your most appropriate next step?
A project consists of multiple phases. Select the valid statements to apply to the interactions of phases.
Members of the project team have requested to be released from their current project to move to another project that has more work. What could be the most likely reason for such a request?
During the Close Procurements process, which organizational process asset must the project manager not forget to update?
A question arises during a discussion with project managers from another division within your company whether a project must be closed if it is canceled. When asked, what is the appropriate response?
Which data analysis technique, used in the Close Project or Phase' process, helps to validate the models used in the organization and to implement adjustments for future projects?
In completing the Close Project process, your team leverages the insights and advice of individuals with specialized knowledge. What type of tools and techniques is the team utilizing?
You are asked by a young project manager what to do during the Close Project process with the project documents that were created and maintained during project execution. Which is the most appropriate answer?
The Closing Process Group contains one process, the Close Project or Phase process. Which knowledge area is this process contained in?
You receive a call from a key stakeholder on the morning of the day you expect to formally close a project. The stakeholder is asking for the status of an open issue that is related to his department. You believe that this issue has been closed, but you are unsure. Which project document should you check to investigate if the issue has been resolved?
During the Close Project process, your team is studying the interrelationships between project variables in an effort to identify and document ideas that could be used to improve performance of future projects. What type of data analysis is your team conducting?
There are five distinct project management process groups. While distinct, the processes within the process groups may be completed in parallel. Which of the terms is the name of a process group?
When completing the Close Project or Phase process, in addition to ensuring that all project work is completed, and the project met its objectives, the project manager must perform activities to conduct a proper administrative closure. Which of the following is not an activity necessary for a successful administrative closure?
For completion of the Close Project or Phase process, a summary must be created that contains validation information related to the final product, descriptions of each phase, and key points related to cost, schedule, and scope performance. What is the name of this document?
In which process group is lessons learned finalized and project resources released?
During the Close Project process, your team is investigating the project's current risk status and attempting to identify if there are any open risks remaining. Which project document should the team leverage to investigate these questions?