PMP (Closing) Questions

Quiz by Amer ali

Our brand new solo games combine with your quiz, on the same screen

Correct quiz answers unlock more play!

New Quizalize solo game modes
20 questions
Show answers
  • Q1

    A key output of the Close Project process is the finalization and archive of the lessons learned register. The register contains information related to best practices identified, project successes and failures, and ideas for future improvements. When during the project should information have been added to the lessons learned register?

    During the Closing Process Group

    Throughout the entire project

    During project execution

    During the chartering process

    120s
  • Q2

    In executing the Close Project process, you have created a final project report, transferred the final product to the ownership of the customer, and dismissed your project team. You believe that you can now formally close the project. What activity have you forgotten to complete?

    Obtain approval from the project sponsor

    Complete and archive the lessons learned register  and all other project documents

    Close the charter document

    Formally acknowledge the success of the team

    120s
  • Q3

    You have just left the final project meeting, during in which you officially transferred ownership of the final product to the customer. In which previous Monitoring and Controlling process did the same customer formally accept the project deliverables?

    Control scope

    Monitor stakeholder engagement

    Monitor and control project work

    Validate scope

    120s
  • Q4

    During the process of completing the Close Project process, you lead your team in analyzing what was planned versus what the results were in the project. The aim of your analysis is to define methods to improve future projects. What data analysis technique are you utilizing?

    Variance analysis

    Trend analysis

    Document analysis

    Regression analysis

    120s
  • Q5

    Unfortunately, this morning you received notification that your project. was canceled. What is your most appropriate next step?

    Email key stakeholders and inform them that the project is cancelled

    Look for anew project

    Investigate and document the reason for termination

    Proceed as normal, a project can not be canceled once it is chartered

    120s
  • Q6

    A project consists of multiple phases. Select the valid statements to apply to the interactions of phases.

    Each phase of the project is considered complete when the project sponsor signs off on that phase

    Each phase is generally concluded  with a review of the work accomplished but is only closed if the next phase has already been started

    Each phase of the project is generally concluded with a review  of the work accomplished and deliverables to determine acceptance and whether the phases should be considered closed

    Each phase is generally concluded  with a review of the work accomplished, but a phase is never considered complete until the end of

    the project, when the entire project can be deemed  complete

    120s
  • Q7

    Members of the project team have requested to be released from their current project to move to another project that has more work. What could be the most likely reason for such a request?

    Their current project has been terminated

    Their current project is nearing completion

    There is less work to be accomplished at the moment due to a  high severity issue upstream

    The members of the team cannot get along with each other

    120s
  • Q8

    During the Close Procurements process, which organizational process asset must the project manager not forget to update?

    Performance reporting

    Procurement audit

    Payment requests

    Lessons learned

    120s
  • Q9

    A question arises during a discussion with project managers from another division within your company whether a project must be closed if it is canceled. When asked, what is the appropriate response?

    0nlyclose projects that have been cancelled if the sponsor demands

    All projects must follow the Project Close process, even if they are canceled

    lf a project is cancelled there is no need to complete the Close Project process

    If cancelled, only projects that have passed the executing process group must complete the Close Project process

    120s
  • Q10

    Which data analysis technique, used in the Close Project or Phase' process, helps to validate the models used in the organization and to implement adjustments for future projects?

    Trend analysis

    Regression analysis

    Variance analysis

    Document analysis

    120s
  • Q11

    In completing the Close Project process, your team leverages the insights and advice of individuals with specialized knowledge. What type of tools and techniques is the team utilizing?

    Expert judgement

    Teamwork

    Data analysis

    Meetings

    120s
  • Q12

    You are asked by a young project manager what to do during the Close Project process with the project documents that were created and maintained during project execution. Which is the most appropriate answer?

    Disregard the project documents, they were only useful in completing the project

    Save all project documents on your work computer and reference them on future projects

    Ensure all project documents are updated, marked as final, and archived

    Transfer them as is to the PMO

    120s
  • Q13

    The Closing Process Group contains one process, the Close Project or Phase process. Which knowledge area is this process contained in?

    Project Integration Management

    Project Scope Management

    Project Stakeholder Engagement

    Project Schedule Management

    120s
  • Q14

    You receive a call from a key stakeholder on the morning of the day you expect to formally close a project. The stakeholder is asking for the status of an open issue that is related to his department. You believe that this issue has been closed, but you are unsure. Which project document should you check to investigate if the issue has been resolved?

    Assumption log

    Change  log

    Issue log

    Risk report

    120s
  • Q15

    During the Close Project process, your team is studying the interrelationships between project variables in an effort to identify and document ideas that could be used to improve performance of future projects. What type of data analysis is your team conducting?

    Trend analysis

    Document analysis

    Regression analysis

    Variance analysis

    120s