
PMP (Cost Management) Questions
Quiz by Amer ali
Feel free to use or edit a copy
includes Teacher and Student dashboards
Measure skillsfrom any curriculum
Tag the questions with any skills you have. Your dashboard will track each student's mastery of each skill.
- edit the questions
- save a copy for later
- start a class game
- automatically assign follow-up activities based on students’ scores
- assign as homework
- share a link with colleagues
- print as a bubble sheet
- Q1
An alert on the project's dashboard indicates that the project's CPI has gone above the upper control limit on the control chart. What should the project manager do?
Wait for the CPI to fall back within the control limits
Find an assignable cause
Communicate the results as a positive outcome
Communicate the results as a negative outcome
120s - Q2
A project manager has taken extra care to identify dozens of individual activity risks on the project and has established reserves for the identified risks. During the gate review to start the execution stage of the project, the steering committee does not approve the project to proceed to execution due to inadequate reserves. What did the project manager most likely forget to do?
Establish management reserves for each identified risk
Assign control accounts to the reserves
Correctly estimate activity costs
Look at overall project risk
120s - Q3
The project is falling behind schedule and is over budget. Nonetheless, there is pressure from the project sponsor to complete the project as planned You must determine what the project's performance must be from this point onwards to achieve the delivery goals.
Which calculation are you most likely to use?
TCPI
SV
SPI
BAC
120s - Q4
One of the key deliverables on the project has been found to contain a defect, and it does not meet project requirements. To scrap the deliverable and replace it would cost $12,000 and take five days to complete. To repair the defect would cost $4,000 and take two days to complete
What should the project manager do first?
Scrap and replace the defective deliverables will increase customer satisfaction
Consult with the project sponsor
Repair the defective deliverables it will have the least impact on the budget and schedule
Submit a change request
120s - Q5
A project manager determines that actual costs to date are $5M and then estimates thatapproximately$4M will still need to be spent to complete the project for a total anticipated expenditure of
$9M. However, the budget for the project is only$8.5M, which is a projected variance of -$0.5M. The anticipated expenditure of $9 MM is documented and reported to stakeholders according to the communications management plan
What has been reported to the stakeholders?
Cost baseline
Cost forecasts
Estimate to complete
Activity duration estimates
120s - Q6
You are a project manager assigned to a bridge construction project Senior management has expressed their concerns regarding cost overruns in labor and materials which may jeopardize the successful completion of the project. You are asked to research the cause and impact of the cost to run and determine if corrective actions are needed.
What tool or technique is most helpful in this situation?
Trend analysis
Earned value analysis
Variance analysis
Reserve analysis
120s - Q7
A project manager is 20 weeks into a project that was planned to be completed in one year. From a schedule perspective, half of the work has already been completed. What are the earned schedule and schedule variance for the project?
26 weeks and 20 weeks
52 weeks and 20 weeks
26 weeks and 6 weeks
20 weeks and 6 weeks
120s - Q8
In preparation for an upcoming project status meeting, you have determined the value of the work completed thus far is $100,000 with a budget at completion (BAG) of $1,000,000. At this point in the project, you have spent 12% of the project budget. The value of work planned to be completed at this point is $115,000 What will you report at the project status meeting?
The project is performing well in terms of cost but not in terms of schedule
The project is not performing well both in terms of cost and schedule
The project is currently over budget
The project is currently behind schedule
120s - Q9
A project manager is planning a project to construct a new multiplex movie theater. As she starts the process of estimating the costs associated with the project, she is unsure whether to use an analogous or bottom-up approach The company has built similar movie theaters in the past, but senior management has a preference for the highest level of detail. What is the best resource to determine the estimating method that should be used for the project?
Basis of estimates
Scope baseline
Cost management plan
Resource management plan
120s - Q10
A project manager is preparing for a status meeting by examining the project's cost performance to date. She produces a chart which depicts the performance of EV, PV, and AC over the past year. The chart reveals that even though costs are over budget, cost performance has been improving over the past four consecutive months. What tool or technique has the project manager used?
Variance analysis
Trend analysis
Root cause analysis
Reserve analysis
120s - Q11
Your project has been in execution for one month, and you have performed earned value analysis (EVA) to determine how the project is performing compared to the cost baseline. Which of the following is the result of your efforts?
Work performance information
Performance measurement baseline
Work performance is data
Work performance reports
120s - Q12
Due to unforeseen challenges, it has been determined that your original budget of $500,000 is no longer realistic. You have estimated that the project will eventually cost $600,000. The table below represents the current status of the project. The method used to determine the earned value is based on percent complete. What is the cost performance efficiency that must be maintained to complete the project based on the estimate at completion?
1.50
0.75
117
0.88
120s - Q13
A project team notices that over the last four work performance reports, the overall costs allocated to a work package are rising steadily, exceeding the funds allocated for this work package What should the project team do next?
Run additional reports from the ensuing time period to determine if the trend continues
Submit a change request to adjust the necessary components of the project management plan
Conduct a trend analysis and root cause analysis to determine the reason(s)
Calculate the TCPI to determine if the work packages still expected to be completed within budget.
120s - Q14
A project manager is in the process of monitoring costs for a hotel construction project and determines that the project is running over budget with a 10% deviation from the baseline plan. What should the project manager do to determine if corrective action is necessary?
Check the cost management plan for a variance threshold
Review the cost register to find the triggers for corrective actions
Speak with the PMO for guidance on the implementation of corrective actions
Perform the Plan Cost Management plan to develop the control thresholds.
120s - Q15
You are preparing to start the process of estimating the costs associated with your new project when a key stakeholder calls you and asks for an estimation of project costs. You provide the stakeholder with an estimate of $1 million with a range of $750,000 to $1.75 million and inform her that you will be able to narrow down the estimate once you are finished with your cost analysis. What have you provided to the stakeholder?
ROM estimate
Analogous estimate
Cost baseline
Bottom-up estimate
120s