- Q1
Per organizational policy any commodities purchased for a project must be either the least cost option available or a sole source. Which project process and tool and technique does this most impact?
Accepted deliverables in Validate Scope
Pre-assignment in Acquire Resources
Source selection in Plan Procurement
Data representation in Identify Stakeholders
120s - Q2
A project manager is leading a project in which a vendor was engaged under a time and materials contract. During a procurement audit, it was discovered that the vendor had been using ghost employees to inflate the cost of the project artificially. As a result, the vendor was terminated for cause. Which organizational process asset is updated to ensure the vendor will not be allowed to work on future projects?
Seller performance evaluation documentation
Lessons learned register
Procurement management plan
Procurement file
120s - Q3
You are managing a project that is nearing its end and planning to settle all pending claims with the vendors. In one case, you are not satisfied with the delivery of their final product. All conversations with the vendor have ended in an impasse What should you do in this situation?
Pay the vendor as some products were delivered
Discontinue further meetings with the vendor and hold back payment
Identify some form of alternative dispute resolution
Take the vendor to court
120s - Q4
A project manager is leading a project to install self-service kiosks. After a bidder conference, one of the prospective vendors asks the project manager if a WiFi connection is required to establish connectivity with the kiosks. The project manager realizes that the WiFi is indeed required but was not discussed at the conference nor was it part of the bid documents. What is the best course of action for the project manager?
Thank the vendor for raising this point and let this vendor know that WiFi access should be delivered
Send a formal letter to all prospective vendors clarifying that WiFi access is part of the bid
Ignore the question as no additional clarifications are allowed after the conference has been concluded
Hold another bidder conference with all prospective vendors to clarify the WiFi requirement
120s - Q5
In a meeting with your team, you discuss the importance of a process that ensures that both your company and the contractors meet procurement requirements You explain that this process is key to managing the contract relationship, monitoring contract performance, and making changes and corrections as appropriate. Which of the following are you describing to the team member?
Conduct Procurements
Project procurement management
Control Procurements
Request management
120s - Q6
You are leading a large and complex project, which requires various vendors and suppliers to provide project deliverables. One of your vendors contacts you and states that they have just completed their contracted work and would like to know when they will receive final payment. How might you respond to the vendor's question?
When we perform project closure, we will release final vendor payments
After we provide you with formal written notice that the contract has been completed
After we have approved all of your deliverables
Once we have verified that you are on our prequalified seller list
120s - Q7
An accounts payable manager withholds the payment for the rental of a piece of equipment The rental company claims the money is due in full because the piece of equipment was necessary to fulfill the objectives of the statement of work defined in the contract. Further talks lead nowhere as both parties cannot come to an agreement. What is the next step for them to take in this situation?
Approach local government officials
Go to court
Attempt alternative dispute resolution
Start direct negotiations
120s - Q8
You are the project manager for a large healthcare organization managing the installation of an electronic medical record (EMR) system. The installation requires a lot of different hardware purchases since this will be the first time an EMR has been used in the organization You have been working through the procurement process, and you are now in the Control Procurements process. Which of the following activities will you perform as part of that process?
Perform source selection analysis
Identify potential sellers
Review sellers' responses
Close contracts with sellers
120s - Q9
During your search for an external contractor, you are evaluating proposals received in response to the bid package. Your evaluation includes ensuring the complete response to the bid documents, procurement statement of work, source selection criteria, and any additional documents that went out in the bid package. What tool or technique are you using?
Joint engagements
Advertising
Data analysis
Selected sellers
120s - Q10
You are finalizing the open claims with the contractor that delivered some of the components for your project. Which project management process are you currently performing?
Procurement audit
Control Procurements
Validate Scope
Close Procurements
120s - Q11
You are managing a project that involves vendors. Midway into project execution, the sponsor hands you a formal letter from the customer informing you that your project has been terminated effective immediately. You are shocked since the project was going well and was forecasted to finish ahead of schedule and under budget What should you do first?
Schedule a meeting with the customer
Close the contracts with the vendors
Have your attorney call the customer's attorney
Continue doing project work until the customer notifies you directly
120s - Q12
The project sponsor is concerned about possible ethics violations between the project and vendors. What independent review can the sponsor order?
Procurement audit
Team assessment
Performance review
Monte-Carlo analysis
120s - Q13
Services are still being billed to the project even though the project manager believes no additional services are required or requested What is the best course of action for the project manager to take?
Close all agreements with all service providers engaged with the project
Forward the service bills to the project management office for further review and approval
Confirm that no more services are needed and the procurement agreements are closed
Continue paying the bills until the project is formally closed to avoid claims
120s - Q14
As you plan your project, you realize that you will need to acquire services from several vendors. However, due to the complexity of requirements, you are concerned that without additional input from the potential sellers, developing an adequate procurement strategy might be difficult What tool or technique would be most helpful in this situation?
Bidder conferences
Meetings with prospective sellers
Make-or-buy analysis
Source selection analysis
120s - Q15
One of your contractors is not performing to the agreed-upon standards. You want to terminate the contract and engage another contractor for the same job. You need to determine the specific legal procedure for the early termination of the contract. What should you do?
Review the risk register
Check the procurement management plan
Consult the contract
Look at the scope statement