
PMP (Resource Management) Questions
Quiz by Amer ali
Feel free to use or edit a copy
includes Teacher and Student dashboards
Measure skillsfrom any curriculum
Tag the questions with any skills you have. Your dashboard will track each student's mastery of each skill.
- edit the questions
- save a copy for later
- start a class game
- automatically assign follow-up activities based on students’ scores
- assign as homework
- share a link with colleagues
- print as a bubble sheet
- Q1
During a sprint planning meeting, the scrum team is arguing over115 story points' worth of user stories that the product owner is pushing to be completed in the upcoming sprint However, the development team's average velocity is only 100 story points.
Who makes the final decision on how many story points will be targeted for completion during a sprint?
The development team
The product owner
The scrum master
The project manager
120s - Q2
A project manager is in the process of obtaining the necessary equipment, materials, and supplies for a prototype development project. The project will require the use of the performing organization's industrial 30 printer, and the project manager has just learned that it is currently committed to another project for the next three days.
What should the project manager do first?
Submit a change request to update the schedule baseline
Negotiate with the other project manager to have exclusive access to the printer
Purchase another3D printer to avoid any potential scheduling conflicts
Document the printer's availability in the resource calendar
120s - Q3
During your project execution, another project that is part of the program to which your project also belongs, submitted a request for a specific engineer who possesses a unique knowledge that your project needs soon.
What is your best action?
Discuss the need with the other project manager
Assign another team member to fulfill the role of the engineer
Escalate the issue to the program manager
Assign the engineer to your project before tile other project can
120s - Q4
Two developers are having a heated argument characterized by personal attacks over who should take a particular user story in the Kan ban board. The project manager steps in and settles the dispute by splitting the user story and having each developer work one aspect of the solution. This action resolves the dispute, but a week later, the same two developers get into another shouting match over how to implement an approved change request. The project manager helps again, but similar conflicts recur almost weekly.
What might the project manager have done differently to avoid these recurring arguments?
Refrained from interfering into the arguments and allowed the two developers to settle their differences as a self-managing team
Ensured WIP limits were assigned to the columns of the Kan ban board to place a constraint on user story assignments
Had the change management plan establish clear roles and responsibilities for the implementation of approved change requests
Analyzed the context for the argument to determine the underlying root cause of the issue between the two developers
120s - Q5
A project team comprised of designers, programmers, and testers uses a Kanban board to manage their workflow. While monitoring the project schedule, the project manager reviews the board and notices a bottle neck at the testing column caused by the WIP limit. As a result, some of the programmers are idled, the team's velocity is slowed, and the schedule baseline is at risk.
What is the best course of action for the project manager?
Lower the testing column WIP limit on the Kanban board
Ask if any of the idled programmers can help with testing
Submit a change request to update the schedule baseline
Remove all of the WIP limits from the Kanban board
120s - Q6
A project manager is following the resource management plan and needs to gain a better understanding of the team members' preferences and aspirations in order to tailor individual developmental activities.
What is the best course of action?
Provide ability tests to the project team members
Schedule structured interviews with each team member
Perform a SWOT analysis
Conduct a team assessment
120s - Q7
Your team has been spending an unusual amount of time arguing in meetings. You have conducted team training to improve meeting discipline and listening skills. Which document should be updated to reflect the new team standards of conduct?
Team charter
Skill assessments
Team register
Issue log
120s - Q8
At the beginning of your project, you were authorized to offer incentives to the designers to work in your company's office building for the duration of the project. You secured a temporary workspace to accommodate the entire project design team in a common area. This strategy allows them to work in proximity to one another to enhance their ability to perform as a unified design team.
What tool or technique did you use in this scenario?
Colocation
Forming
Virtual teams
Strategic placement
120s - Q9
A project has reached a critical point, and a decision must be made immediately to salvage the project from failure. The project manager meets with the projectteam and key stakeholders. The meeting runs for a few hours, but the participants are unable to agree on anything
What should the project manager do?
Schedule another meeting in a week from now
Select an option and make a decision
Call in the HR manager to calm everybody down
Try to find a solution that works for everybody
120s - Q10
During project execution, a major supplier goes bankrupt. After conducting root cause analysis, the project team determines that a shortage of raw materials was the reason for the supplier to go out of business. The team researches and explores various options, and decides to hire another supplier, even though it will raise costs. After the new supplier delivers on the contract, the team reviews project performance information to determine if the project's resource needs have been met.
Which of the following best describes the technique being employed in this scenario?
Root cause analysis
Problem solving
Supplier analysis
Alternatives analysis
120s - Q11
You take over a project that has just been baselined. You review the project management plan and realize that while the development phase of the project will use an adaptive lifecycle, the development team does not have any experience with agile methodologies. The resource management plan does not specify any agile training
What should you do first?
Submit a change request to revise the project management plan
Adjust the roles and responsibilities in the resource management plan
Change the life cycle description of the development phase to predictive
Hire an agile coach to assist with the development phase of the project
120s - Q12
A company wants to improve the performance of its agile teams. Most of the team members work remotely for various reasons. The senior management team seeks advice from an agile coach as to the best approach that would have the biggest positive impact on teams' performance. The management says that funds are not an issue and nothing is off-limits.
What would be the best advice the agile coach can provide to the company's management?
Upgrade the team's computers with the latest technology to increase work productivity
Purchase additional software tools to improve the team's remote communication
Colocate the team members to improve team collaboration and communication
Assign a cubicle to each team member to help them better maintain their focus
120s - Q13
An experienced agile practitioner was explaining the benefits of empowered, self-organizing, and self-directing teams. Some agile team members then complained that their manager is not very agile as demonstrated by their very directive style of communication.
How would the agile practitioner most likely respond to this comment?
The project has a very tight schedule and must be managed by directives.
The team is still in the storming stage, which requires a lot of direction
The team is already in the norming stage, which requires a lot of direction.
Theory is one thing, and real life is a totally different story.
120s - Q14
Mid way into project execution, a team member suggests using a new testing method that, if successful, would save the team time in each consecutive iteration and eventually put the project ahead of schedule. If the new testing method is unsuccessful, however, the entire performance measurement baseline might need to be revised.
What is the best course of action for the project manager?
Instruct the team to start using the new testing method from the next iteration onward
Submit a change request and let the team decide whether to use the new testing method
Request the product owner to create a user story that describes the new testing method
Decline the suggestion since it may threaten the performance measurement baseline
120s - Q15
Asa project manager, you are leading a century-old building renovation project, where theft of equipment, materials, and supplies has been a problem. You have found that moving anything of value that is portable into a single secured room of the building has significantly reduced the losses with minimal cost.
What should you do next?
Discuss the situation with the team during the next retrospective
Add the daily security task to the milestone schedule
Include the information in the lessons learned repository
Include the information in the lessons learned register
120s