  • Q1

    You are leading a project to renovate a sports stadium. The project has a hard deadline as the work must be completed before the start of the games season. Upon developing and optimizing the schedule, the total float for the project is negative. The project sponsor is adamant that the project must be completed on time at any cost As you try to find the solution, you realize that none of the activities can be overlapped. What is your best course of action?

    Perform resource smoothing to bring the schedule into alignment with project goals

    Shorten the schedule duration by the least incremental cost by adding resources

    Schedule some activities on the critical path to be performed in parallel instead of in sequence

    Do nothing as negative float implies the schedule is adequate to complete the project on time

    120s
  • Q2

    Midway into project execution, you have been asked to shorten your project duration by three weeks to meet a new deadline but deliver all originally planned functionality. Additional resources are available, and the cost is not as great a concern as schedule. What should you do?

    Crash activities on the critical path

    Remove external dependencies

    Reduce project scope

    Level resources

    120s
  • Q3

    An agile team wants to apply a tool to visually analyze their work in progress for each step in a process in order to determine where bottlenecks exist in the overall process. What tool would help them the most?

    Control chart

    Kanban board

    Cumulative flow diagram

    Release burndown chart

    120s
  • Q4

    A project manager is monitoring the status of the project schedule for a product development project. The project deliverables are being produced in an iterative fashion, and the project has just completed seven of twelve planned sprints The project manager has gathered the following information:

     • 17 story points were completed and accepted in the seventh sprint • 20 story points were planned for sprint #7

    • One feature worth 3 story points was completed but rejected and placed back in the product backlog

    • The value of the features developed to date is $172,000

    • Actual costs to date are $167,000

    • The BAG for the project is $300,000

    • The project backlog contains 250 story points

    • The project team has successfully completed 137 story points to date Which of the following accurately describes the schedule performance of the project for the seventh iteration?

    There is not enough information in the scenario to determine the schedule performance

    The schedule variance (SV) is -3 story points, and the schedule performance index (SPI) is 0.85

    The schedule variance (SV) is O story points, and the schedule performance index (SPI) is 1.0

    The cost variance (CV) is $5,000, and the cost performance index (CPI) is 1.03

    120s
  • Q5

    Understanding the various metrics that are generated during an agile project allows agile practitioners to more accurately gauge the scope, time, and resources needed to complete a project and deliver incremental value with each iteration. For the purposes of gauging the number of iterations needed to complete a project, a correct understanding of throughput is essential. Which of the following statements describes what is meant by throughput in agile terms?

    The length of time it takes for a feature to deliver value, from the moment that the team begins to work on it, to when it is finished and accepted.

    The amount of time it takes for a feature to go through the entire process from requirements gathering to deployment.

    The number of iterations that can be successfully completed by a team during a single release.

    The number of user story points that can be successfully processed by a team during a single iteration

    120s
  • Q6

    A project to build a software application is being managed using a lean framework for software development An agile practitioner creates a value stream map to analyze the process and see how to reduce the time between when a user story is submitted to the team as a requirement from the customer and when it is deployed at the customer production environment as a product increment and starts delivering value. Which of the following is the agile practitioner trying to minimize or reduce?

    Lead time

    Waste

    Work in progress

    Cycle time

    120s
  • Q7

    A project team has just completed estimates for both the activity durations and the activity resources for the project you are managing. Tomorrow morning, you need to present a preliminary schedule to the key stakeholders. What is your best course of action?

    Apply resource optimization techniques

    Develop the schedule management plan

    Present the project schedule network diagram

    Pre-assign the resources required for the project

    120s
  • Q8

    Looking at your network diagram, resource calendars, and the risk register, you learn that one of your key resources on one non-critical path is scheduled to undergo minor surgery and will be out for seven days. Another key resource has a planned vacation for five days, and another is presenting at a conference for three days, and their assigned activities affect the critical path. To proactively protect your milestones, what can you add to your project schedule using the critical chain method?

    Both project buffers and feeding buffers

    Both divergence and convergence

    Both early start and late start

    Both total float and free float

    120s
  • Q9

    A project is underway to construct a wind farm in an area with no communication infrastructure. The plan is to monitor progress and coordinate the scheduling of the project activities using project management software and provide daily status updates to the project sponsor at the home office. Two project teams will work and reside onsite in rotating seven-day tours. Which of the following is the most likely challenge the teams will face while controlling the schedule?

    Stability of requirements

    Human resource availability

    Project importance

    Technology support

    120s
  • Q10

    During the first iteration planning meeting, an agile team struggled to provide an accurate estimation of their velocity. Someone quoted a well-known British economist, John Maynard Keynes, by saying: "It is better to be roughly right than precisely wrong." Which of the following best describes the meaning and intent of this statement?

    The velocity estimation

    Progressive elaboration

    Rolling wave planning

    The cone of uncertainty

    120s
  • Q11

    You are advising a project manager who is new to your company and has just been assigned to manage a project The sponsor on his project is very demanding and is asking to see a project schedule developed as soon as possible. The project manager would like to meet the sponsor's request and produce a project schedule as quickly as possible but without jeopardizing work quality. Which of the following represent the best advice for the project manager in this case?

    Develop the activity list, then the WBS and WBS dictionary

    Develop the WBS and activity list concurrently using the project manager's expertise, rather than the whole project team

    Develop the WBS and activity list concurrently with the help of project team members

    Ask senior management for a new sponsor within the company

    120s
  • Q12

    The project is supposed to roll out a new service to thousands of existing users. The project team wants to consider and prepare for various possibilities and situations that may occur during rollout. What technique can the project manager facilitate to help the team with their preparations?

    Critical path method

    What-if scenario analysis

    Fast tracking technique

    Statistical sampling

    120s
  • Q13

    A project manager had originally planned to use two industrial 3D printers simultaneously for a project but has just learned that one of them will be unavailable. The project manager adjusts the schedule so that the components are created sequentially using one printer Unfortunately, this action affects the critical path and delays the planned finish date of the project. What tool or technique has the project manager used in this situation?

    Crashing

    Fast tracking

    Resource smoothing

    Resource leveling

    120s
  • Q14

    As the project manager, you are analyzing the project schedule and discover that the project is behind schedule due to shipment delays and inclement weather. You want to bring current project performance into alignment with the original planned schedule. What is your best course of action?

    Applly resource smoothing

    Apply resource leveling

    Adjust the leads and lags

    Adjust the level of effort

    120s
  • Q15

    Midway into project execution, new cybersecurity laws take an immediate effect and require audits of the system The project has a well thought out project management plan. The audits may come at any time throughout the system's development What is the best way for the project manager and team to address the risk of audits disrupting the project plans?

    Request that the sponsor removes the audits

    Handle the audits as an unplanned spike

    Reschedule the audits to the end of the project

    Inform stakeholders that the project will miss its objectives

    120s