Project Cost Management
Quiz by Sinjini B
Feel free to use or edit a copy
includes Teacher and Student dashboards
Measure skillsfrom any curriculum
Measure skills
from any curriculum
Tag the questions with any skills you have. Your dashboard will track each student's mastery of each skill.
With a free account, teachers can
- edit the questions
- save a copy for later
- start a class game
- automatically assign follow-up activities based on students’ scores
- assign as homework
- share a link with colleagues
- print as a bubble sheet
9 questions
Show answers
- Q1AC = 6000, PV = 4000, EV = 3000, the project currently isbehind schedule and under budgetbehind schedule and over budgetahead of schedule and under budgetahead of schedule and over budget30s
- Q2PV = 5000, AC = 4000, EV = 3500, the project currently isbehind schedule and under budgetahead of schedule and over budgetbehind schedule and over budgetahead of schedule and under budget30s
- Q3AC = 6000, PV = 4000, EV = 5000, the project currently isbehind schedule and under budgetbehind schedule and over budgetahead of schedule and under budgetahead of schedule and over budget30s
- Q4PV = 4500, AC = 4000, EV = 5000, the project currently isbehind schedule and under budgetbehind schedule and over budgetahead of schedule and over budgetahead of schedule and under budget30s
- Q5If a project has a Schedule Performance Index (SPI) of 0.90, this means that:90% of the work of the whole project has been completed90% of the budget planned..to date..has been spent90% of the work planned to date..has been..completed90% of the project budget has been..spent30s
- Q6If a project has a Cost Performance Index (CPI) of 0.90, this means that:111% of the project budget has been spent90% of the budget planned to date..has been spent90% of the work planned to date..has been completed111% of the budget planned to date..has been spent30s
- Q7A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of 0.80. The project is currently...behind schedule and over budgetbehind schedule and under budgetahead of schedule and over budgetahead of schedule and under budget30s
- Q8According to EVM, which..term below represents the..outstanding amount of money required to finish the project?PVEACETCEV30s
- Q9According to EVM, which..term below represents the..budgeted cost of the work to be completed to date?ETCPVEVEAC30s