Project Management
Quiz by Nicky Trajano
Feel free to use or edit a copy
includes Teacher and Student dashboards
Measure skillsfrom any curriculum
Measure skills
from any curriculum
Tag the questions with any skills you have. Your dashboard will track each student's mastery of each skill.
With a free account, teachers can
- edit the questions
- save a copy for later
- start a class game
- automatically assign follow-up activities based on students’ scores
- assign as homework
- share a link with colleagues
- print as a bubble sheet
35 questions
Show answers
- Q1All of the following are subsidiary elements of the project management plan except:Project scope statementScope baselineRisk management planQuality management plan120s
- Q2Which of the following best describes a focus group?Group of cross-functional stakeholders who can define cross-functional requirementsGroup of subject matter experts who participate anonymouslyOne-on-one conversations with stakeholdersGathering of prequalified subject matter experts and stakeholders who provide feedback120s
- Q3Jin is currently in the planning stages of a project and is working on developing the project scope statement. As part of converting the product scope description into deliverables, he has used the product breakdown and systems analysis techniques. Which of the following tools and techniques of the Define Scope process is Jin currently using?Data analysisExpert judgmentProduct analysisInterpersonal and team skills120s
- Q4The following are included within the WBS dictionary except:Cost estimatesCode of accounts identifiersDescription of the work of the componentActivity list120s
- Q5While sequencing activities, a project manager decides to use the precedence diagramming method to show existing dependencies between activities. Which of the logical relationships is the project manager most likely to use?Finish-to-startStart-to-finishFinish-to-finishStart-to-start120s
- Q6The scope management plan should contain the following information except:The list of all the requirements to be included in the scopeThe process used to prepare the project scope statementThe process used to create the WBSThe definition of how deliverables will be checked for accuracy and the process for accepting deliverables120s
- Q7Which of the following is the purpose of collecting requirements?Creating a clear billing structure for project reimbursementEstablishing the order in which activities should be conductedDocumenting stakeholder expectations for meeting the project objectiveDetermining the total budget that will be needed for the project120s
- Q8What is the correct definition of a project constraint?Project constraints never change during the project.Project constraints limit the options of the project team.Project constraints are conditions presumed to be true.Project constraints do not affect project outcomes.120s
- Q9Which of the following quality theorists devised the zero defects practice?Philip B. CrosbyJoseph JuranWalter ShewhartW. Edwards Deming120s
- Q10All of the following are tools and techniques of the Plan Quality Management process except:Operational definitionMeetingsBenchmarkingFlowcharts120s
- Q11What is the correct definition of a critical path task?A critical path task is a project activity with zero float.A critical path task is a project activity with schedule flexibility.A critical path task must be done before all other project activities.A critical path task does not affect the project schedule.120s
- Q12What is the cost baseline?The barrier to entry to attempt the projectThe source of all project fundingThe total budget allocated to the projectThe authorized, time-phased cost of the project120s
- Q13Which definition of the cost of quality (COQ) is correct?COQ increases the overall budget of the project.COQ is the total cost to produce the product meeting the quality standards.COQ is cost associated with parts from a high-quality supplier.COQ is a project forecast that is displayed on an S curve.120s
- Q14All of the following are benefits of meeting quality requirements except:Reduction in reworkIncreased stakeholder satisfactionIncreased costs for the projectHigher productivity120s
- Q15Bebe is a project manager for a data center consolidation project. During a recent planning meeting, she collected estimates for how long it would take to configure all of the switches within the new location. Tyra, who will be the lead for performing the activity, noted that if all goes well, it would take the team 15 hours, although she noted most likely closer to 20 hours. In a worst case, it would take the team 50 hours, provided that multiple issues arise. Based on Tyra’s estimates, what is the estimate that Bebe will use as the duration of the activity if she were to calculate it based on a beta distribution?24 hours28 hoursInsufficient information20 hours300s