Quiz 1
Quiz by salma zaghloul
Feel free to use or edit a copy
includes Teacher and Student dashboards
Measure skillsfrom any curriculum
Measure skills
from any curriculum
Tag the questions with any skills you have. Your dashboard will track each student's mastery of each skill.
With a free account, teachers can
- edit the questions
- save a copy for later
- start a class game
- automatically assign follow-up activities based on students’ scores
- assign as homework
- share a link with colleagues
- print as a bubble sheet
10 questions
Show answers
- Q1Which of the following is NOT a characteristic of a project?Constrained by limited resourcesPlanned, executed, and controlledCreates a unique product or serviceOngoing and repetitive60s
- Q2Your company is responsible for developing an anti-virus software. You are responsible for managing both the individual product releases and the coordination of multiple releases. Your role is that of a:Functional managerProject managerProgram managerOperations manager60s
- Q3If a project manager is concerned with gathering, integrating, disseminating, the outputs of all project management processes, he should concentrate on improving the:Communication management planProject management information system(PMIS)work break down structure(WBS)Scope management plan60s
- Q4A project manager has little project experience but she has been assigned as the project manager of a new project. because she will be working in a matrix organization to complete her project, she can expect communications to be:Open and accurateComplexSimpleHard to automate60s
- Q5A project manager has to manage different stakeholder expectations. Project sponsor and customer are two very important stakeholders in any project. In this context, which of the following is NOT the responsibility of both the project sponsor and the customer?Provide key events, milestones, and deliverable due datesFormally accept the product of the projectTake into account risk toleranceProvide financial resources for the project60s
- Q6All of the following are true about the project scope management plan EXCEPT:It can be formal or informal, broadly framed or highly detailed, based on the needs of the project.It describes how the scope will be defined, developed, monitored, controlled, and validated.It enables the creation of the WBS from the detailed project scope statement.It is not related to the project management plan.60s
- Q7You are developing a document that links product requirements from their origin to the deliverables that satisfy them to help ensure that each requirement add business value and to manage changes to the product scope. This is known as the:New product development matrix.Requirements traceability matrix.Configuration management system.Business case.60s
- Q8The following is an example of a constraint associated with the project scope that limits the team's options in scope definitionThe method used to measure project performance.A predefined budget or any imposed dates or schedule milestones that are issued by the customer or performing organization.The threat of a stroke by a subcontractor.Existing relationships with sellers, suppliers, or others in the supply chain.60s
- Q9In rolling wave planning:Focus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activities.The work to be accomplished in the near term is planned in detail, whereas the work in the future is planned at a higher level.The work far in the future is planned in detail for work packages that are at a low level of the WBS.A wave of detailed activities is planned during strategic planning to ensure that WBS deliverables and project milestones are achieved .60s
- Q10Which of the following is NOT an output of the Control Scope process?Accepted deliverables.Project documents updates.Change requests.Work performance information.60s