Scope Management
Quiz by Marina
Feel free to use or edit a copy
includes Teacher and Student dashboards
Measure skillsfrom any curriculum
Measure skills
from any curriculum
Tag the questions with any skills you have. Your dashboard will track each student's mastery of each skill.
With a free account, teachers can
- edit the questions
- save a copy for later
- start a class game
- automatically assign follow-up activities based on students’ scores
- assign as homework
- share a link with colleagues
- print as a bubble sheet
10 questions
Show answers
- Q1All of the following are true about the Project Scope Management plan EXCEPTIt enables the creation of WBS from the detailed project scope statementIt describes how the scope will be defined, developed, monitored, controlled and validatedIt can be formal or informal, broadly framed or highly detailed, based on the needs of the projectIt is not related to the Project Management Plan30s
- Q2You are developing a document that links product requirements from their origin to the deliverables that satisfy them to help ensure that each requirement adds business value to manage changes to the product scope. This known as the:Configuration management systemBusiness caseRequirement traceability matrixNew product development matrix30s
- Q3The following is an example of a constrain associated with the project scope that limits the teams options in scope definitionA predefined budget or any imposed dates or schedule milestones that are issued by the customer or performing organizationExisting relationships with sellers, suppliers or others in the supply chainThe method used to measure project performanceThe threat of a strike by a subcontractor30s
- Q4In rolling wave planningThe work far in the future is planned in detail for work packages that are at low level of the WBSThe work to be accomplished in the near term is planned in detail, whereas the work in the future is planned at a higher levelFocus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activitiesA wave of detailed activities is planned during strategic panning to ensure that WBS deliverables and project milestones are achieved.30s
- Q5Which of the following is NOT an output of the Control Scope process?Change requestsWork performance informationAccepted deliverablesProject document updates30s
- Q6Agile scope planning is specially useful whenScope is well understood at the beginningSolution requirements are emerging all the timeBusiness requirements are not stableQuality requirements are not stable30s
- Q7An output of the define scope process isResource breakdown structure (RBS)Project scope statementWork breakdown structure (WBS)Scope and Schedule delays control plan30s
- Q8All of the following are true about the project scope statement EXCEPTIt is an output of the validate scope processIt may contain explicit scope exclusions that can assist in managing stakeholder expectationsit describes in details the project deliverables and the work required to create those deliverables.It provides a common understanding of the project scope among the project stakeholders30s
- Q9You are managing a global project that invlves stakeholders in several international locations. You likely consult the WBS dictionary to findStrengths, weakness, opportunities, and threat (SWOT) of key stakeholders and their impact on WBSDetailed deliverable, activity and scheduling information about each component in the WBSInformation relating the legal constrains of relevant international locations to the development of the WBSThe language translations of technical terms used in the Project30s
- Q10All of the following are true about the control Scope process EXCEPTControl scope is the process of monitoring the status of the project and product scope and managing changes to the scope baselineScope changes can be avoided by developing clear and concise specifications and enforcing strict adherence to themControl scope is used to manage the actual changes when they occur and and is integrated with the other control processesControlling the project scope ensure that all requested changes and recommended corrective or preventive actions are processed through the perform Integrated Change Control process30s