Let's consider a simple example of a manufacturing process to calculate Value Time Percentage (VTP).Â
1. Value-Adding Activities: - Cutting raw materials to size - Assembling components - Quality inspection of finished products
2. Non-Value-Adding Activities: - Waiting time for the next step - Material handling between workstations - Redoing defective products
Now, let's assume the time taken for each activity in the manufacturing process:
- Cutting raw materials: 30 minutes
- Assembling components: 45 minutes
- Quality inspection: 10 minutes
- Waiting time: 20 minutes
- Material handling: 15 minutes
- Redoing defective products: 25 minutes
Calculate VTP Percentage for the above!