placeholder image to represent content

PMP (Risk Management) Questions

Quiz by Amer ali

Our brand new solo games combine with your quiz, on the same screen

Correct quiz answers unlock more play!

New Quizalize solo game modes
30 questions
Show answers
  • Q1

    You have started gathering documents you need to implement a planned response to a realized risk. You need a document that will provide summary information on identified risks, as well as an assessment of the current project risk exposure. What is the input document you need?

    Risk Report

    Assumption log

    Project Charter

    Lessons learned register

    120s
  • Q2

    A project manager is preparing for a meeting to identify risks associated with the project. As part of the preparations, the project manager is looking for a document that captures a comprehensive list of factors that could either benefit or constrain the project Which of the following would help the project manager the most?

    Assumption register

    Project charter

    Assumption log

    Risk register

    120s
  • Q3

    The risk management plan for the project stipulates that the project holds risk review meetings weekly. Which of the following are you least likely to do during these meetings?

    Updating the risk report

    Creating the risk register

    Capturing knowledge gained in the lessons learned register

    Revising the issue log

    120s
  • Q4

    A team member is working on a project activity where the outcome did not go as planned, but this outcome was expected as a possibility. Which of the following should the team member consult to know what to do next?

    Project schedule

    Risk response plan

    Business case

    Schedule diagram

    120s
  • Q5

    At a planning meeting with the stakeholders, an executive requested to see a top-down representation of all types of uncertainty for the project. Which of the following should the project manager use to categorize sources of project uncertainties to address the executive's request?

    Bar chart

    Risk breakdown structure (RBS)

    Work breakdown structure (WBS)

    Risk audit

    120s
  • Q6

    A project manager is leading an infrastructure development project and is just starting the process of prioritizing individual project risks for further analysis.  A stakeholder has expressed concern that the existing information about individual project risks may not be accurate and reliable. What is the best course of action?

    Perform a risk data quality assessment

    Perform the Identify Risks process again

    Conduct a risk probability and impact assessment

    Capture the concern in the stakeholder register

    120s
  • Q7

    The project keeps running into similar errors. The project manager is surprised, as she had plans in place to mitigate these errors. What is most likely the root cause of these errors?

    Not enough meetings are held

    Having repeating errors is normal for any project

    Risk response plan not being implemented

    Incompetent project team members

    120s
  • Q8

    You and your project team have recently discovered a negative risk to the project and determined that it could result in a loss of S50,000 if it occurs. You have also determined that the probability of this risk occurring is 50%. What is the expected monetary value for this risk?

    $250,000

    -$250,000

    -$25,000

    $25,000

    120s
  • Q9

    A software development project is running behind schedule because the velocity of the project team has been slowed down by a higher than anticipated complexity of the technology used to develop the product. To bring the project back into alignment with its objectives, the project manager implements the planned response by fast tracking some of the testing activities. What should the project manager do next?

    Submit a change request to update the schedule baseline to reflect the results of fast tracking

    Submit a change request to update the issue log with the final resolution

    Update the schedule using the project management information system (PMIS)

    Update the risk register to add the newly identified  risk of higher than anticipated complexity

    120s
  • Q10

    A project manager is in the process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness.  Which of the following is least likely to be updated as a result of this process?

    The risk register

    Test and evaluation documents

    The lessons learned register

    The issue log

    120s
  • Q11

    As a project manager, you will need the assistance of other stakeholders in order to identify the risks associated with your project. You want to determine who are the individuals that might participate in the process of identifying risks to the project, as well as those who are available to act as risk owners. Where should you look?

    Stakeholder register

    Risk breakdown structure (RBS)

    Project charter

    Responsibility assignment matrix(RAM)

    120s
  • Q12

    During project planning, the project manager involves the product owner and scrum team in the Plan Risk Responses process. A critical product feature is under discussion, and no one is certain that the feature can even be developed given the current technology. The project manager adds this risk to the risk register and indicates it as exit criteria in the project charter. What is the best risk response strategy to deal with this threat?

    Performa reserve analysis and ensure that adequate management reserves reset a side to address this specific threat

    Transfer ownership of the risk to a third party by buying insurance so that the third party bears the impact if the threat occurs

    Ask the product owner to mitigate the impact of the risk by prioritizing the critical feature at the top of the project backlog

    Assign the project sponsor as the risk owner since the exit criteria are specified in the project charter, which is owned by the sponsor

    120s
  • Q13

    Halfway into a software development project, your most experienced programmer resigns leaving only two programmers. The previously planned response to this risk is to acquire a programmer from another project manager, with whom you are not well acquainted.  What is the best way for you to handle this situation?

    Escalate to the project sponsor

    Ask the remaining two programmers to work overtime to cover the gap

    Use your authority as a project manager and demand the release of the other programmer

    Use your soft skills

    120s
  • Q14

    As a project manager, you are in the process of prioritizing individual project risks. The project team has just completed a probability and impact matrix, and you have decided to consider other characteristics of risk when prioritizing individual project risks. What should you do next?

    Run a Monte Carlo simulation

    Conduct a risk probability and impact assessment

    Perform an assessment of other risk parameters

    Complete a risk data quality assessment

    120s
  • Q15

    A project is chartered to install an IT data center in a foreign country where the political climate is highly unstable. To address the threat to the data center due to the political instability, the project manager has negotiated with the U.S. State Department to establish the data center in a high-security basement of the U.S. Consulate.  This is an example of:

    Risk transfer

    Risk mitigation

    Risk avoidance

    Risk acceptance

    120s

Teachers give this quiz to your class